EPSILON: Developing gas pipeline infrastructure in Kashkadarya region in cooperation with Uzbekneftegaz
Сonstruction of three gas pipelines continues: “Nazarkuduk collecting point – Shurtanneftegaz” (67 km), “Tandircha CP – Shurtanneftegaz” (45 km) and “Chigil CP – Mubarek gas processing plant” (110 km). Pneumatic testing (stage one) of “Nazarkuduk CP – Shurtanneftegaz” pipeline is in progress.
The speed of round-the-clock construction is, on average, 4 km per day.
Total for December 11:
• 36,000 t of pipes shipped;
• 23,600 t of pipes arrived;
• 62.4 km of trenches dug;
• 94.4 km of pipes welded;
• 51.5 km laid.
Epsilon Press Office