EPSILON: Developing gas transportation system in Kashkadarya in cooperation with Uzbekneftegaz
Round-the-clock construction of three gas pipelines continues: “Tandircha CP – Shurtanneftegaz” (45 km), “Chigil CP – Mubarek GPP” (110 km) and “Talimarjon CP – Shurtanneftegaz” (8 km).
Total for December 17:
- 43,700 t of pipes shipped;
- 28,100 t of pipes arrived;
- 90.3 km of trenches dug;
- 111.7 km of pipes welded;
- 71.2 km laid.